Biomethane Pralboino 250 Smc

Project information

Development and construction of a 250 kWe biogas plant

The SYNERGY team, in cooperation with METHODO and SWITCH, part of the BIOMETHANE INDUSTRY group, is completing the revamping of a 250 kWe biogas plant for the production of 250 Smc/h of Biomethane, intended to be fed into the grid.

The plant, which will be managed by the agricultural company ‘Le Rebusche’ of Pralboino (BS), will be powered by renewable energy sources. Planned interventions include: the installation of new pre-tanks to feed the digesters, the upgrading of the anaerobic biomass digestion units, in mesophilic regime, for the production of biogas, and the upgrading of the digestate storage tanks. In addition, a new nitro-denitro treatment tank will be built.

The project also includes the installation of a desulphurisation tower for Biogas pre-treatment, an upgrading unit for refining Biogas into Biomethane, and a new compression unit for feeding Biomethane into the grid.

Input matrices

  • Pig slurry
  • Cattle manure
  • Poultry manure

Technical description

Pollina pre-tank
diameter 10 metres - height 4 metres
Slurry pre-tank
diameter 10 metres - height 4 metres
New fermenters
diameter 30 metres - height 8 metres
Gas recovery storage tank
no.1 diameter 30 metres - height 9 metres
Final storage tanks
no.1 diameter 24 metres - height 8 metres, no.1 diameter 30 metres - height 8 metres
Desulphurisation tower
bio-chemical desulphuriser with a nominal capacity of 500 Nmc/h of biogas.
Solid biomass loading hopper
Capacity 100/114 m3
SBR plant
Input capacity 150 t/d